22.07.2013 What does company need to be successful, authoritative and to gain social acceptance?
·
01.10.2010 Laying of high-voltage CL in Ukraine - the experience of "SVS-DNIPRO" company. Elektropanorama # 9, 2010.
·
16.06.2010 Vladimir Vypyraylo: motto of "SVS-DNIPRO" – always be on step ahead of!

Name
E-mail

GISMETEO: Погода по г.Киев
Finalized projects · 2013 projects
2013 projects
Name of project Type of executed works Specification
 SS 750 kV “Kyivskaya”
Construction and electrical installation works, installation of equipment
 Works for extension are executing on an operating substation. A big scope of construction work was performed for construction of following buildings:

  • Indoor transformer substation 10 kV (ITS-10 kV)
  • Building of relay panels №1(BRP-1)
  • Building for combined operational and repair purposes
  • Building for repairing of SF6 equipment
  • Chamber for switching of valves №2, and №4
  • Apparatus room of mineral oil facilities
  • Installation of foundations for group of reactors with construction of fire protector partitions between reactors and dry pipe sprinkler system was completed
  • Installation of 5 reactors 750 kV was completed
  • All foundations for portals and equipment 750 kV were installed
  • 14 portals with upper bus arrangement made from hollow aluminum wire with cross-section 500 mm2 were installed
  • 80 000 m2 of substation`s territory covered by broken brick
Photo
Dnistrovska pumped-storage hydro station (PSHS)
Construction and electrical installation works, installation of equipment
During 2013 under realization of 1st stage of construction of Dnistrovska pumped-storage hydro station that includes three hydroelectric units a complex of electrical installation works for taking into operation of block№2 was completed, namely:
  • Installation of bay №3 in SF6 GIS-330 kV;
  • Installation of portal’s bay Я330 and flexible connection 330 kV SF 6 GIS-330 kV-2T;
  • Installation of 2 groups of current-limiting reactors with voltage 15,75 kV;
  • Installation of excitation system of hydroelectric units №2, excitation transformer, cable connections between transformer and excitation system, current conductor of DC;
  • Installation of aggregative and plantwide panels of auxiliary needs 0,4 kV with transformers 6,3/0,4 kV and cable lines 6,3 kV and 0,4 kV;
  • Installation of generator’s breakers and disconnectors 15,75 kV;
  • Installation of DC system and cable lines of DC=220V
  • Installation of main and standby protection systems of block №2 and aggregate controller of block №2;
  • Installation of cabinets for temperature and vibration monitoring of hydroelectric unit №2.
A full complex of electrical installation work under laying and connection of the cable lines of secondary circuits for full-fledged work of above mentioned equipment was completed.
An execution of all works in time allowed to put into operation of hydroelectric unit №2 in mode of synchronous compensation and to proceed to the first stage of its complex testing
Photo
Reconstruction of electrotechnical part of equipment of block №6 of branch office of “Kanivska hydro-electric power station (HPP)" There were installed: the excitation system and excitation transformers manufactured by ALSTOM, generator circuit-breakers 6,3 kV manufactured by ABB, generator disconnectors, current and voltage transformers 6,3 kV, generator current leads manufactured by DURESCA, current-limiting reactor, cabinets and panels for auxiliaries needs, current and voltage transformers 110 kV, surge protection device 110 kV, earthing switches 110 kV, disconnectors 110 kV, technical water supply system, drainage system; laid more than 40 000 m of cable connections, performed redecoration of control system room on altitude +100,500.
There were performed fire protection works of cable penetrations through walls, partitions and floors in rooms of Kanevskaya HPP.
There were completed installation of ventilation system in Indoor Switch Gear of block №6 as well as lighting and power supply of control system room on altitude +100,500.
There were completed works for replacement of cabinets of oil-immersed devices and cable lines to pumps of oil-immersed devices
Photo
Construction works on site “Overhead power transmission line 750 kV Zaporozhska NPP –Kahovskaya with SS 750 kV “Kahovska” with stopping of Overhead power transmission line 330 kV”. Start-up complex №3 (Reconstruction of SS 330 kV “Novokahovska” with replacement of AT 220/150/35 kV by AT 330/220/35 kV) There were completed works under 35 kV cable lines laying with stabbing of concrete slabs УБК-5 and backfill of trench on 35 kV cable line ЕМЗ-1, ЕМЗ-2, Schorsa-1, Schorsa -2, Berislav.
There was laid 6 kV cable line between auxiliary transformer and arc-suppression coil 6 kV and ISG 35/6 kV
There was laid around 4 km of different cables for auxiliary systems of substation
There were installed and equipped with busbars circuit breakers 154 kV in bays №3 and №6 on OSG 150 kV.
In annex of substation control house there were installed auxiliaries board, DC board, 22 relay panels, laid electrical networks for lighting system and power supply for ventilation system.
In relay panels building there were installed 48 relay panels, laid power supply network for ventilation system
There were completed installation works of reinforced concrete poles for equipment of arc-suppression coil 35 kV
There were completed construction work for cable canals and sinks between T1, T2 and building of ISG 35/6 kV.
There was completed construction work for foundation of light tower №37
There was completed construction work for foundation pit for oil catcher AT1
There was completed digging of track of firefighting pipeline on territory of OSG 150 kV as well as installation of wells for connection of new firefighting pipeline to existing fireproof tank.
There was completed internal and external redecoration of annex building to substation control house (except installation of underroof and stone riprap of building.

Photo
Improvement of power supply for tobacco factory OJSC “Tobacco factory Priluky” There were completed all construction and electrical installation works, namely:
  • construction and installation works under construction of bay 35 kV on OSG-35 kV of SS 110/35/10 kV “Priluki”
  • construction and installation of SS “Tobacco factory” 35/10 kV. On this substation there were installed power transformer 10 MVA and metal clad switchgears 35 kV and 10 kV in module type buildings. There were installed bays КУ-35, КУ -10Ц manufactured by RZVA with circuit breakers and microprocessor protection devices and automatics manufactured by ABB.
  • construction and installation works under laying of cable line 35 kV from SS “Priluki” to SS “Tobacco factory”. This cable line has length 5,150 km through Priluki city with transition under the bottom of Uday river which was made by horizontal directional drilling method.
  • construction and installation works under reconstruction of factory’s internal power supply networks 10 kV and laying of cable line 10 kV from SS “Tobacco factory” 35/10 kV to existing switch gear 10 kV.
  • balancing and commissioning works, acceptance testing, taking into operation.
Organization of work and their implementation were executed with appropriate quality control and according to agreed schedule of work execution. The work was done at high professional level taking into account of all requirements of design, technological and regulatory documents and also in full concordance with safety regulations and fire safety.
Photo
Reabilitation of HV substation of Dniper Power Grid System. Reabilitation of SS 330 kV “Dniprodzerzhincka" There were completed all construction and electrical installation works, balancing and commissioning works and took into operation the bays: ВВ Л-191 150 кV, ВВ Ш-331 330 кV, ВВ Ш-2 150 кV, ВВ Л-233 330 кV, ВВ С-2 150 кV, Л-15 150 кV
Photo
Reabilitation of HV substation of Dniper Power Grid System. Reabilitation of SS 330 kV “Pivdena” There were completed all construction, electric installation works, balancing and commissioning works and took into operation the bays: ВВ Л-КС-2 150 кV, ВВ Л-КС-1 150 кV , ВВ Л-207 330 кV , ВВ Л-54 150 кV, ВВ АТ-2 150 кV, ВВ Л-29А 150 кV
330/110/10 kV SS « Severnaya». Expansion and reconstruction
  At reconstruction of 330 kV SWYD the following equipment, which operation life had finished, was replaced:
  • air circuit-breaker were replaced with SF6 ones – 2 pieces

  • single-pole disconnectors – 18 pieces

  • current transformers – 2 pieces

  • voltage transformers – 2 pieces

  • surge arresters - 5 pieces.

    On 330 kV SWYD, five damaged reinforced concrete gantries in “AT-1” and “AT-2” bays were also replaced with metal ones and bus arrangement was replacement with АС 400/51 wire.

    Within the scope of the reconstruction works on 110 kV SWYD, there were performed replacement of the following equipment:

  • Replacement of 20 pcs. of oil circuit breakers with SF6 ones for arrangement of 110-8 circuit (two operational sectionalized circuit breakers and transfer busbars with two bus coupler circuit-breakers).

  • Replacement of 59 pcs. of three-pole disconnectors which operation life had finished with remote controlled disconnectors:

  • ShR-110-I - 20 pcs.

  • ShR-110-II - 19 pcs.

  • LR-110 - 10 pcs.

  • OR-110 - 10 pcs.

  • There were replaced 11 pcs. of current transformers

    Also, on 330 kV SWYD, there were replaced 20% of damaged line reinforced concrete gantries with metal ones. Due to the fact that the territory of 110 kV SWYD is limited, there were installed molded metal gantries manufactured by Kromiss-Bis company.

    There were performed reconstruction of substation control building-1, auxiliary service building and 10 kV indoor switchgear building (AT-1).

    There were performed installation of reactors and 10 kV bays inside of 10 kV indoor switchgear (AT-1).

    There was performed recovery of substation roads on 330 SWYD kV and 110 kV SWYD.

    There were laid around 90 km of power and control cables.

Photo
Relay protection and Automation for 750 kV Substations Energy facilities and enterprises automation systems There were performed works on reconstruction and replacement of relay protection and automation devices due to replacement of 330-750 kV existing air circuit breakers with SF6 ones at seven 750 kV substations of consolidated power system of Ukraine on the following feeders:
  • 750 kV substation “Zakhidnoukrains’ka”:

    750 kV VVR-5, 11V-12, 11V-2, VVR-6, 7V-1, 3V-12, 3V-2

    330 kV V-82, V-72, V-110, V-112, V-71

  • 750 kV substation “Pivdennodonbas’ka”

    750 kV ZAES 1 SSh, ZAES 2 SSh

    330 kV Zarya-1 1SSh

  • 750 kV substation “Vinnyts’ka”

    750 kV 1V, 2V, 5V, 6V

    330 kV V-30, V-31, V-32

  • 750 kV substation “Zaporizhs’ka”

    750 kV L-Don / 1, L-Don / 2, VRSh-Donb

    330 kV L-202

  • 750 kV substation “Dniprovs’ka”

    750 kV L-ZAES / 2, L-ZAP

    330 kV VP-5, L-267/1, L-267/2

  • 750 kV substation “Donbas’ka”

    750 kV AT-4 1SSh

    500 kV NV AES 2SSh, Peremoga 2SSh, Peremoga 1SSh

    330 kV UTES №1 2SSh, UTES №1 1SSh

  • 750 kV substation “Pivnichnoukrains’ka”

    750 kV 2V, VOR

    330 kV 80V, 82V

    Development of design estimate documentation

     

Solar power station which is located outside of populated localities of Mykolaivs'ka Soviet of the village, in area of village Vinnitsky of Simferopol district in AR Crimea and belongs to LLC “Kapella solar”
Electrical installation works, installation of equipment
  • Complex of electrical installation works for creation of power output scheme 10 kV and optical communication links;
  • Complex of electrical installation works for creation of auxiliary power supply scheme for voltage 10kV and 0,4 kV ;
  • Reconstruction of power output scheme 10 kV and optical communication links;
  • Reconstruction of auxiliary power supply scheme for voltage 10 kV and 0,4 kV
Photo
Solar power station which is located outside of populated localities of Mykolaivs'ka Soviet of the village, in area of village Vinnitsky of Simferopol district in AR Crimea and belongs to LLC “Yupiter solar” Electrical installation works, installation of equipment
  • Complex of electrical installation works for creation of power output scheme 10 kV and optical communication links;
  • Complex of electric installation work for creation of auxiliary power supply scheme for voltage 10kV and 0,4 kV ;
  • Reconstruction of power output scheme 10 kV and optical communication links;
  • Reconstruction of auxiliary power supply scheme for voltage 10 kV and 0,4 kV
Photo
Development of design estimate documentation
Reconstraction of cable line 110 kV “Octyabrska” – ПУ-31 SS – Mototsykletna №1, 2 Design works Customer – PJSC “Kyivenergo”
Working design: reconstruction of existent cable-overhead line 110 kV from SS 330 kV “Oktyabrskaya” to SS 110 kV “Mototsykletnaya” with replacement of overhead section SS 330 kV “Oktyabrskaya” - ПУ - 31 and oil filled cable form ПУ – 31 to SS “Mototsykletnaya” by cable 110 kV with XLPE insulation. Total length of new cable line 110 kV is 3,8 km. Type of cable is 2XS(FL)2Y-WTC 1x630RM/120 64/110/126 kV, manufactured by TF Cable. The working design was transferred to customer in full scope.
Construction of cable line 110 kV “Novokyivska – Moskovska №1,2” Design works Customer – PJSC “Kyivenergo”
Working design: Construction of new cable lines 110 kV from SS 330 kV “Novokievskaya” to SS 110 kV “Moskovskaya” with stopping to SS 110 kV “Odesskaya”. Total length of new cable lines 110 kV is 16 km. Type of cable - 2XS(FL)2Y-WTC 1x1400RM/150 64/110/126 kV, manufactured by TF Cable (type of cable is not final).
In 2013 there were completed topographic works and land measuring with plotting M1:2000, M1:500 , calculation of operating modes of network 110 kV
Relay protection and automatic for substations 750 kV
Design works Customer – SE “NPC” Ukrenergo”
Working design: reconstruction of relay protection and automatic due to replacement of existing air circuit-breakers 330-750 kV by SF6 circuit-breakers on following substations 750 kV: “Vinnitskaya”, “Zaporozhskaya”, “Donbasskaya”, “Yuzhnodonbasskaya”, “Zapadnoukrainskaya”, “Severoukrainskaya”, “Dneprovskaya”. The working design was transferred to customer in full scope. Positive expert grades of Ukrgosstroyexpertiza were received
Cement plant in Lenin district of Autonomous Republic of Crimea on base of Krasnopartizanskiy limestone deposit which has productivity 3 million tons of clinker in year. External power supply.
Design works Customer – LLC “Altcem”
Working design: reconstruction of existing OSG-110 kV of SS 220 kV “Kamysh-Burun” in scope of expansion on two line bays, construction of double-circuit overhead line 110 kV from SS 220 kV “Kamysh-Burun” to SS 110 kV “Altcem”.
There were performed circuit diagrams of relay protection and automatic from SS 110 kV “Altcem” side.
Construction of shopping and office complex with public facilities and parking on Sportivnaya square 1 in Pechersk district of Kyiv
Design works Customer – LLC “Three O”
Working design documentation and detail design: making alterations in design documentation on the customer's request on stage “Detailed design”, designing of detachable transformers T17 and T18 by 1MBA each of them for TS 1 and increasing of allowable attachable load on stage “Detailed design”, designing of cable lines for tenants on level +37,600 and +41,500 on stage “Detailed design”.
Working design documentation and detail design were transferred to customer in full scope.
Construction of shopping and office complex with public facilities and parking on Sportivnaya square 1 in Pechersk district of Kyiv Design works Customer – LLC “Three O”
Working design documentation: design of external decorate lighting.
Working design documentation was transferred to customer in full scope.
Internal power supply of cinema complex “Planeta kino” on leased area in block №1 in shopping and office complex “Gulliver” on Sportivnaya square 1 in Pechersk district of Kyiv
Design works Working design: designing of internal electric lighting and electric power equipment of cinema complex “Planeta kino”.
Working design was transferred to customer in full scope.
Construction of shopping and office complex with public facilities and parking on Sportivnaya square 1 in Pechersk district of Kyiv (floor 28)
Design works Customer - LLC “TRI O”
Working design documentation: designing of internal electric lighting and electric power equipment on 28th floor in office part of complex.
Development of working design documentation is on the final stage
Garages Staronavodnitskaya

Headquarters:
4a, Promyslova St., Kiev, 01013
Phone: +38 (044) 545-71-24, 25
Production facilities:
4, Shkilna St., Vyshgorod, 07301
Phone: +38 (044) 430-36-17, 451-67-21,
+38 (04496) 54-9-23
 
© 1993 - 2018 SVS-Dnepr PrJSC . All rights reserved.